Asia project cargo demand surges, but roads and bridges can't keep up

Executives at Breakbulk Asia warn Asia's project cargo boom is outpacing infrastructure, with 500-1,500-tonne modules facing road and bridge bottlenecks.

By
Tom Whitfield
Filed
Length
701 words
Read
4 min
Project cargo boom in Asia hobbled by inadequate infrastructure
Project cargo boom in Asia hobbled by inadequate infrastructurepixel2013 / pixabay

Key points04

  • Asia project cargo demand is expected to surge, but transport capacity is lagging project development, executives said at Breakbulk Asia in Singapore.
  • Denzai CEO Kohki Uemura cited roads and bridges as bottlenecks for modules weighing 500 to 1,500 tonnes.
  • AAL's Felix Schoeller linked the boom to 10 years of China Plus One manufacturing shifts across South-east Asia and India.
  • Ceva's Yohan Beal said clients now seek logistics approval before purchase orders are signed.

Demand for project cargo across Asia is set to surge in the near term, yet the industry's capacity to move those shipments is struggling to keep pace — and the weakest link sits on land, not at sea. That was the blunt message from executives speaking at Breakbulk Asia in Singapore today, where carriers, forwarders and EPC specialists lined up to flag infrastructure gaps that could stall modules weighing between 500 and 1,500 tonnes.

MSC's head of project cargo, Ben Collins, said Asia is becoming increasingly central to executing major infrastructure and industrial projects, and framed the moment in unusually confident terms. "Vietnam has an emerging nuclear power programme; Asia is very central to the supply and successful delivery of these projects, so it's time for optimism and bullishness," he told the event.

What's driving the boom?

The commercial pull is geopolitical as much as industrial. Felix Schoeller, commercial chief of multipurpose operator AAL Shipping, said shifting trade politics have accelerated the relocation and expansion of engineering, procurement and construction (EPC) activity across the region.

"There has been a big push in the last 10 years, going back to the first Trump administration, which resulted in the China Plus One strategy, boosting manufacturing capacity across South-east Asia and India," Schoeller explained.

Ten years of factory diversification. The result: more heavy-lift cargo originating in Vietnam, India and South-east Asia, and more EPC work awarded to Asian yards and suppliers.

Where does the chain break?

Oversize and heavy cargo hits its first wall well before the vessel. Kohki Uemura, CEO of Japanese heavylift forwarder Denzai, identified road and bridge infrastructure as the dominant bottleneck when moving modules in the 500-to-1,500-tonne range. "Roads and bridges are not enough for such heavy cargo," he said.

For shippers, that constraint bites in a specific way. A module that can be lifted, loaded and sailed may still be undeliverable over the final kilometres between port and project site, and route engineering — not ocean capacity — becomes the binding limit on project schedules.

Who owns the fix?

Yohan Beal, Ceva Logistics' operations director for Asia Pacific, put responsibility squarely with the parties running logistics surveys and overseeing project requirements. His questions were direct. "Is due diligence being done?" he asked. "Can I make sure that I can actually get the cargo out of the port? Can I actually deliver the cargo from the port to the final destination?"

"Those are the parameters we need to ascertain before we actually fix the port of discharge and the final route we take," he added.

Beal also noted a structural shift in how projects are run: owners and EPC contractors now bring specialist logistics providers into planning far earlier than they once did. "Since the pandemic, people who used to be underappreciated in the logistics field are now making their way to the boardrooms. Clients now seek approval before purchase orders are signed," he said.

That change carries commercial weight for forwarders and carriers alike. Earlier involvement means earlier influence over port selection, routing and packaging decisions — and a stronger negotiating position for specialists who can prove landside feasibility before contracts are locked.

Collins echoed the call for earlier planning, and warned project owners against chasing short-term cost savings at the expense of future transport requirements. "Don't be dictated by looking for a cheaper price tomorrow… what you might have to move today is going to cost you more tomorrow," he said.

What does this change for shippers?

In practice, three things. First, feasibility studies must cover the full landside chain — roads, bridges, port egress — before the port of discharge is fixed, not after. Second, logistics specialists now sit at the table before purchase orders are signed, giving them a veto they rarely held pre-pandemic. Third, cheap procurement decisions made today can translate into premium transport costs tomorrow when heavy modules meet inadequate infrastructure.

The trajectory executives sketched in Singapore points one way: with China Plus One investment, Vietnam's nuclear programme and broader EPC expansion feeding the pipeline, project cargo volumes in Asia look set to grow faster than the roads and bridges meant to carry them.

Source: The Loadstar

Share this article:

More from Tom Whitfield

Tom Whitfield

Show full bio

Market editor covering companies, deals and strategy in Ocean and air freight, container shipping at Waybill Wire.

938 articles

Related05

  1. Central Asia needs $33bn annually as air cargo charter gaps widen

  2. Cambodia Positions Itself as Southeast Asia's Next Supply Chain Hub

  3. Central Asia needs $33bn a year in infrastructure, but the air capacity doesn't fit

  4. Vietnam and Japan target $80 billion trade, eye supply chain shift

  5. Tariffs rewrite sourcing maps as Asia corridors hold, costs pile up