Uganda pays Shs373bn to 7,721 claimants to unlock Malaba-Kampala rail corridor
Uganda has paid Shs373.07bn to 7,721 of 12,946 claimants, securing 2,108 of 3,536 acres for the 272km Malaba-Kampala SGR linking to Mombasa via Kenya's rail network.
- Desk
- Trucking & Rail
- By
- Tom Whitfield
- Filed
- Length
- 673 words
- Read
- 3 min

Key points05
- Uganda has paid Shs373.07 billion to 7,721 of 12,946 project-affected persons for the Malaba-Kampala SGR corridor.
- Government now possesses 2,108 of the 3,536 acres needed; Shs472.45 billion in compensation remains outstanding.
- Contractor Yapı Merkezi completed a €75 million Limited Notice to Proceed in October 2026; full works await financial close.
- About 98% of a continuous corridor between Malaba and Mayuge is acquired, giving roughly 130km of workable route.
- The 272km Eastern route will connect Uganda to Kenya's SGR network and the Port of Mombasa.
Uganda has paid out Shs373.07 billion (about $99 million) to 7,721 people to clear land for the Malaba-Kampala Standard Gauge Railway — roughly 60% of the 12,946 project-affected persons on the 272-kilometre Eastern route.
The compensation has given the state possession of 2,108 acres of the 3,536 acres required to start works, Works and Transport Minister Fred Byamukama told Parliament on Tuesday 17 November. The remaining Shs472.45 billion owed to outstanding claimants will be paid at a later date.
That's the commercial core of the story: land, money, and a contractor waiting to move.
Where does construction actually start?
Byamukama was blunt about geography. "Land acquisition is most advanced between Malaba and Mayuge, where approximately 98 per cent of a continuous corridor has been acquired," he said. "We now have adequate corridor of approximately 130km where the contractor can start works."
Compensation and acquisition continue, with priority going to construction-critical sections. In plain terms, the Turkish contractor can now work a contiguous 130km stretch from the Kenyan border inland, while the state keeps buying the rest of the right-of-way.
The contractor is Yapı Merkezi, and it is already on site — sort of. Government issued the firm a Limited Notice to Proceed (LNTP) valued at €75 million (Shs341.63 billion) for preparatory works while financing for full construction is concluded. The LNTP commenced on 14 May 2025 and completed in October 2026.
Its scope covered surveys, geotechnical investigations, and procurement of essential equipment, including earth-moving machinery. Byamukama's verdict: "Implementation of the LNTP activities has reduced technical uncertainty and established capacity to support the transition to full construction. The LNTP remains a preparatory arrangement pending financial close and issuance of the full Notice to Proceed."
That sentence tells you the project's real gate. Not land anymore — money. Full works hinge on financial close.
What does the line change for Uganda's cargo economics?
Once built, the Malaba-Kampala SGR connects Uganda to Kenya's SGR network and the Port of Mombasa. The route is designed to improve access to regional and international markets, shifting transit freight from road to rail on East Africa's main import-export artery.
For shippers and forwarders moving cargo between Kampala and Mombasa, that is the long-game prize: a standard-gauge alternative to the road corridor through Malaba.
What did MPs push back on?
Shadow Works and Transport Minister Asinansi Nyakato (PFF, Hoima City Woman Representative) argued that delayed compensation of project-affected persons has inflated the project's cost. She also pressed the minister on climate provisions.
"We want the Minister for Works to clarify how much money has been put in the budget to cater for climate risks. We resolved in the 11th Parliament that budgets for transport infrastructure construction should cover climate risks," she said.
Byamukama replied that Shs11 billion is earmarked in the project budget to safeguard the environment, and that the figure will increase where need arises.
Abdul Bisaso (NRM, Kassanda County South) raised a different grievance: constituents living in fear of displacement despite holding legitimate land titles near the project area. "Staff from Uganda Railway Corporation came and demarcated their houses which are far from the land owned by the corporation. The people who demolish houses do not respect local leaders and do not give notices," he said, asking the minister to send a team to open boundaries so residents aren't displaced.
The minister's answer was unsentimental. The Kassanda demolitions hit property found inside the railway reserve. "We are doing this to save government money that would have been paid in compensation to individuals who have built in areas gazetted for the railway. We shall do boundary opening where the corridor is contested with the public," Byamukama said.
With 98% of the Malaba-Mayuge corridor secured and the LNTP wrapped, the next marker to watch is financial close — and with it, the full Notice to Proceed that converts a 130km workable corridor into a 272km railway.
Source: africa.com
More from Tom Whitfield
Show full bio
Market editor covering companies, deals and strategy in Ocean and air freight, container shipping at Waybill Wire.
938 articles
Related05
Uganda paid Shs109.8bn for SGS assets, but most still sit unregistered
Vitol to develop Tanzania-Zambia petroleum corridor upgrades
$155bn infrastructure bill: Africa's mining boom redraws logistics map
Dangote puts $2.2bn into Nigeria's roads as 14,000-truck fleet grinds on broken highways
1,350 km CAR–Kribi Rail Could Add 70-80 Capesizes a Year