Gothenburg's Skandia Gateway quay work done, dredging starts
Gothenburg finishes 700m of quay reinforcement on budget; Boskalis starts removing 230,000 m³ of material for a 17.5m-draught berth due in 2027.
- By
- Amara Osei
- Filed
- Length
- 625 words
- Read
- 3 min

Key points05
- 700 metres of Gothenburg's south quay reinforcement completed on schedule and within budget after two years of NCC works.
- Blasting and dredging by Boskalis Sweden began October 13, removing 200,000+ m³ of soft material and ~30,000 m³ of rock.
- Berth designed for 17.5m draught; quay works due to finish March 2027, fairway works to start August 2027.
- Larger vessels up to 430m long and 65m wide expected to call from the turn of 2028 to 2029.
- Port and Swedish Maritime Administration aim for full operations before the end of 2028.
The Port of Gothenburg has finished reinforcing 700 metres of its container terminal's south quay on schedule and within budget, clearing the way for blasting and dredging works that began on October 13. More than two years of complex civil works by contractor NCC are done. Now the diggers get loud.
The milestone moves the Skandia Gateway project into its next major phase. Boskalis Sweden takes over the sharp end: blasting and dredging the first 50 metres of water alongside the westernmost 700 metres of the south quay. The job involves removing more than 200,000 cubic metres of soft dredged material plus roughly 30,000 cubic metres of rock — enough rock, for scale, to fill about 12 Olympic swimming pools.
The berth is designed for vessels drawing up to 17.5 metres, with works expected to complete in March 2027.
What does this change for carriers and shippers?
The practical answer arrives at the turn of 2028 to 2029, when larger container vessels with deeper draughts will be able to call at Gothenburg. Skandia Gateway is being designed to accommodate boxships up to 430 metres long and 65 metres wide. That's 30 metres longer and five metres wider than the biggest vessels the terminal handles today, with draughts up to four metres deeper.
Put simply: Scandinavia's largest container port is aligning itself with the biggest ships currently trading, not the ones that called a decade ago.
Elin Dörrheide, project manager for quay reinforcement at the Port of Gothenburg, described the completion as the result of excellent collaboration and confirmation that the project is making strong progress. She framed the scheme as strategically important for Swedish industry's access to global markets, at a moment when several major European container ports face constraints in water depth and capacity.
That constraint point matters commercially. If deep-draught capacity is scarce elsewhere in northern Europe, a port that can take a 17.5-metre vessel without tidal fudging becomes a routing option rather than a fallback. For carriers, it widens the set of ports where the largest tonnage can rotate profitably. For Swedish shippers, it shortens the distance between their factories and the mainline network.
The fairway still has to follow
The quay is only half the equation. In parallel, the Swedish Maritime Administration is procuring more extensive blasting and dredging in the fairway and turning basin, alongside modifications to navigational aids. A contract is planned for early 2027, with works scheduled to begin in August 2027.
The shared ambition of the port and the maritime administration is for both the new fairway and the quay to become operational before the end of 2028. Ambition, as ever in European port construction, is easier to schedule than to deliver — but the quay phase landing on time and on budget suggests the programme's project controls are holding.
NCC's reinforcement works, running since spring 2024 along the westernmost stretch of the south quay, were a technically complex precondition for everything that follows. You cannot deepen water next to a quay wall that hasn't been strengthened to take it. That groundwork is now banked.
Why depth is the story
Gothenburg's bet is straightforward. Vessels keep growing; many European gateways physically cannot follow. A port that can berth a 430-metre ship at full draught gives carriers flexibility and gives Swedish exporters a direct connection to the deepest networks rather than feeder-dependent routings.
With dredging now underway, a March 2027 berth completion date, and fairway works starting August 2027, the critical path runs straight to the end of 2028. If the fairway contract lands on time, Gothenburg's first 17.5-metre-draught calls should follow within months of the turn of the decade.
Source: Container News
More from Amara Osei
Show full bio
Staff writer covering regulation, policy and their impact on Ocean and air freight, container shipping at Waybill Wire.
431 articles
Related05
Gothenburg Port Lands New Timber Rail Service Linking Dalarna to Asia and MENA
Gothenburg restarts rail freight for Fiskarheden forest exports
Fiskarheden launches 44-FEU rail shuttles from Dalarna to Gothenburg
Hutchison and MSC reopen Omega talks as Rotterdam sets January 2027 cutoff
Antwerp-Bruges Starts Quay Renewal at Hansa Dock, Running to 2028