WW/PORTSTERMI
Gothenburg Fairway Deepening Contract Priced at $230 Million
A $230 million joint-venture award targets a 16.5-meter fairway at Gothenburg by autumn 2028, with an option for 17.5-meter vessel drafts and work due to start in August 2027.
- By
- James Calloway
- Filed
- Length
- 671 words
- Read
- 3 min

The Swedish Maritime Administration has awarded a base dredging contract worth approximately $230 million (SEK 2.3 billion) to deepen and widen the fairway serving the Port of Gothenburg.
The selected joint venture comprises Boskalis Sweden AB, Van Oord Sweden AB and Rohde Nielsen A/S. Contract signing is planned for the end of 2026 between the administration, Gothenburg Port Authority and the consortium, provided the award faces no legal challenge.
What will the deeper fairway change?
Skandia Gateway will increase Gothenburg’s available vessel draft to 16.5 meters by autumn 2028, compared with 13.5 meters today. The administration’s announcement says the project will “make it possible to receive today’s largest container vessels fully laden, as well as even larger vessels in the future.”
- Current draft: 13.5 meters.
- Base-project target: 16.5 meters by autumn 2028.
- Option target: 17.5 meters.
- Dredging volume: About 7 million cubic meters of loose dredged material and rock.
- Base value: About $230 million, or SEK 2.3 billion.
- Work window: August 2027 to autumn 2028.
The Port of Gothenburg is the largest port in the Nordic region and a central link between Swedish industry and global markets. The current depth limits how much cargo the largest container vessels can carry to and from the port, so the 3-meter increase matters most to the largest container vessels serving Gothenburg.
What does the contract cover?
The base assignment covers dredging approximately 7 million cubic meters of loose dredged material and rock, plus changes to the fairway markings. At that scale, Skandia Gateway ranks among Sweden’s largest dredging projects.
The wider project also includes adaptations to the quay and port basin. Those works sit alongside the fairway contract: quay reinforcement has finished under Port of Gothenburg management, and a separate dredging package close to the quay is already underway.
How did the procurement change after cancellation?
The previous procurement was cancelled in autumn 2025. The revised project then optimized the fairway design and reduced the dredging scope before the new award. The announcement does not give a reason for the cancellation or quantify the reduction from the earlier procurement.
Quayside work continued under Port of Gothenburg management while the fairway was reprocured. That sequencing keeps the quay and basin works moving despite the reset, while the new contract concentrates the award on the revised channel, dredging and navigation-marking scope.
What does this mean for cargo customers?
The commercial benefit is cargo access. Gothenburg can receive today’s largest container vessels fully laden once the base project opens, instead of holding those ships below their available cargo capacity because of the present channel depth.
For carriers, the deeper route supports deployment of the largest vessels on services calling Gothenburg and creates a path to even larger ships if the port orders the option work. No carrier has announced a vessel commitment or service change with the award, so the announcement establishes port capability rather than a new sailing rotation.
For shippers and forwarders, the 16.5-meter target broadens the draft profile available at Gothenburg and can support larger loads through the port’s existing global-market role. The announcement provides no TEU-capacity gain, cargo-volume target or handling-cost estimate, so draft access is the only quantified commercial improvement.
When will the capacity arrive?
The next binding milestone is contract signing at the end of 2026, which remains contingent on the award facing no legal challenge. Fairway work is scheduled to begin in August 2027, with the entire Skandia Gateway project due for completion in autumn 2028.
Until then, the base improvement remains a construction program rather than available capacity. The additional deepening required for 17.5-meter drafts sits behind an option with no stated call-off date, price or vessel commitment.
Gothenburg’s 16.5-meter gain has a defined autumn 2028 horizon, but the move to 17.5 meters depends on a future option decision, leaving the deeper-draft proposition uncommitted beyond the base project.
Source: maritimeprofessional.com
More from James Calloway
Show full bio
Correspondent covering companies, deals and strategy in Ocean and air freight, container shipping at Waybill Wire.
930 articles
Related05
Gothenburg's Skandia Gateway quay work done, dredging starts
Gothenburg Port Lands New Timber Rail Service Linking Dalarna to Asia and MENA
DOF lands $100m-$200m African subsea contract for Skandi Seven
Gothenburg RoRo volumes up 5% after three-year investment push
Stockholm Norvik Inaugurates Aggregate Loading Facility for Baltic Bulk Trades