WW/PROCUREMEN
SCG's $5bn Long Son petrochemical complex to restart in Q2 2027
SCG says its $5bn Long Son complex in Vietnam will restart in Q2 2027, ahead of plan, as a $500mn upgrade to run on 1mn tonnes a year of US ethane is accelerated.
- By
- Elena Vasquez
- Filed
- Length
- 593 words
- Read
- 3 min

Key points05
- SCG's $5bn+ Long Son complex in Vietnam will resume operations in Q2 2027, earlier than originally planned.
- Production was suspended around May 2026 after Middle East feedstock supply was disrupted by regional conflicts.
- SCG is investing about $500mn to enable ethane use and signed a 15-year contract for roughly 1 million tonnes of US ethane per year.
- Vietnam revenue reached about $1.9bn in the first nine months of 2026; group adjusted cash EBITDA rose 19% to $1.76bn.
- Duy Tan broke ground on a VND900bn ($35mn) plastics factory expansion in Tay Ninh Province.
Thailand's SCG Group says its $5 billion Long Son Petrochemical Complex (LSP) in Vietnam will resume operations in the second quarter of 2027, brought forward from the original timeline as the company races to complete a roughly $500 million upgrade allowing the plant to run on US-imported ethane gas.
The announcement came on Tuesday alongside SCG's business results for the first nine months of 2026. The complex, which began commercial production in September 2024, suspended output around May 2026 after regional conflicts disrupted feedstock supplies from the Middle East. It was the second shutdown in the facility's short operating history.
The restart now hinges on the ethane conversion project, which SCG says it is accelerating. Once complete, the upgrade is expected to give the plant greater flexibility in feedstock selection, cut production costs and strengthen competitiveness in a global petrochemical industry still under pressure.
What does the ethane deal look like?
SCG has locked in supply for the long term. The company has signed a 15-year contract covering approximately 1 million metric tons of ethane annually, imported from the United States. At roughly $500 million, the upgrade investment equals about a tenth of the complex's total capital cost of more than $5 billion.
The commercial logic is straightforward: swapping exposure to Middle East supply routes for a contracted American feedstock stream insulates the plant from the kind of geopolitical disruption that idled it in May. For chemical shippers and tanker operators, a restarted LSP also rebuilds demand on ethane and petrochemical trade lanes into Southeast Asia.
How is SCG performing in Vietnam?
Revenue from SCG's Vietnamese operations reached VND48.996 trillion, about $1.9 billion, in the first nine months of 2026. That performance sits within a broader group recovery: adjusted cash EBITDA hit VND45.341 trillion ($1.76 billion), up 19 percent year on year, while profit rose 13 percent and sales revenue gained 3 percent.
SCG President and CEO Thammasak Sethaudom said Vietnam continued to be an important market in the group's long-term growth strategy. "Despite facing fluctuations in energy prices and geopolitical uncertainties, SCG continued to invest in projects, human resources and partnerships in Vietnam," he said.
The group's footprint in the country underlines that commitment. SCG currently operates 28 subsidiaries in Vietnam with more than 15,000 employees across petrochemicals, building materials, packaging and logistics.
Where else is the money going?
Beyond Long Son, SCG is expanding downstream in plastics. Duy Tan Plastics Manufacturing JSC, a member of SCG Packaging, has broken ground on an expansion of the Duy Tan Long An Plastics Factory in Tay Ninh Province. The project carries an estimated investment of VND900 billion, nearly $35 million.
The expansion deepens SCG's integration in Vietnam, linking imported resin and domestic petrochemical output to packaging and plastics manufacturing closer to end customers.
Why the timeline matters
The second-quarter 2027 restart target is earlier than SCG originally planned, a signal the group wants the plant generating revenue sooner as the industry grapples with thin margins. Each quarter of downtime at a $5 billion complex represents a substantial drag on group earnings, making the accelerated ethane upgrade as much a financial decision as an operational one.
For Vietnam, the return of one of its largest industrial investments would restore a major domestic source of polypropylene and other petrochemical products, reducing reliance on imports in the interim. Attention now shifts to whether the US ethane supply chain and the conversion works stay on schedule through 2026 and into 2027.
Source: news.tuoitre.vn
More from Elena Vasquez
Show full bio
News editor covering people, launches and day-to-day practice in Ocean and air freight, container shipping at Waybill Wire.