Long Thanh airport misses 2026 opening as Vietnam reviews phase 1 timeline

Airports Corporation of Vietnam says Long Thanh's terminal packages cannot finish in 2026, proposing a phase 1 extension to 2027-28 as the government demands a report within a week.

By
Tom Whitfield
Filed
Length
835 words
Read
4 min
Vietnam's Long Thanh airport opening tied to safety requirements, project timeline under review
Vietnam's Long Thanh airport opening tied to safety requirements, project timeline under reviewpixel2013 / pixabay

Key points

  • ACV says component project 3 cannot be completed in 2026 and proposes extending phase 1 to 2027-28
  • Deputy PM Pham Gia Tuc ordered a report to the Ministry of Construction within a week; ministry must report before December 10
  • Terminal, cargo terminal No. 1, parking and airport systems are expected to be completed or finish trial runs in June
  • Access expressways and An Phu interchange largely complete only in early Q2-2027
  • Vietnam Airlines and Vietjet warn simultaneous construction and operations pose safety and service risks

Long Thanh International Airport will not open in 2026. Airports Corporation of Vietnam (ACV), the project investor, told a meeting in Hanoi on Wednesday that component project 3 — the package covering the passenger terminal, cargo terminal No. 1, parking facility and airport management systems — cannot be completed on schedule, and asked the government to consider pushing phase 1 implementation to 2027-28.

Standing Deputy Prime Minister Pham Gia Tuc chaired the session and ordered ACV to deliver a full report to the government and the Ministry of Construction within a week, with the ministry submitting a progress report before December 10 so authorities can consider adjusting the investment policy.

For an airport meant to relieve Tan Son Nhat and anchor cargo growth in Vietnam's southeast corridor, the slippage carries real costs. Airlines plan networks and cargo capacity years ahead, and ground infrastructure contractors now face funding questions.

What went wrong with component project 3?

ACV laid out three groups of problems. None of them is small.

  • Materials and equipment deviations. Some deliveries differ from contract specifications in manufacturer, brand, type and origin. Orders, deliveries and installation went ahead before the investor approved the changes and before contract amendments were signed.
  • Design mismatches. Some completed works were built and accepted on construction drawings that do not match the approved technical design — and the corresponding technical design adjustments have not been made.
  • Work started early. Other construction began before construction drawing documents were approved.

ACV said resolving these issues is necessary for construction acceptance and approval to put the airport into operation. The big packages — passenger terminal, cargo terminal No. 1, parking facility and airport management systems — are still expected to be completed or finish trial runs in June.

What does the delay change for airlines and forwarders?

Vietnam Airlines and Vietjet told the meeting they are preparing to operate at Long Thanh in line with approved plans, but warned that simultaneous construction and operations could pose risks to safety and service quality. Vietnam Airlines added that airlines need sufficient preparation time, particularly for international flights, because passengers often book tickets months in advance. Any airline that built 2026 schedule assumptions around Long Thanh now has to redraw them.

Vietnam Air Traffic Management Corporation flagged a dependency: some remaining work under component project 2 depends on infrastructure completion under component project 3. It proposed prioritizing technical facilities and infrastructure connections so air traffic management systems can be deployed.

Government response and deadlines

Tuc ordered agencies to resolve project obstacles without legitimizing existing violations or allowing new ones. Investors, ministries, agencies and local authorities must handle what falls within their authority and escalate the rest. ACV bears full responsibility to the government and prime minister for the progress and quality of component project 3 and its construction packages.

The deputy PM also directed ACV to:

  • Review payment issues and resolve them in line with regulations so contractors have enough funding to continue work.
  • Assess the quality and suitability of the materials and equipment facing problems.
  • Review all remaining work under component project 3 and set deadlines for construction, equipment installation, trial runs, operational testing and the earliest possible opening date.
  • Devise dust-control measures and ensure phase 1 operational safety while phase 2 is under construction.

The Ministry of Construction will monitor and inspect project progress and guide ACV on investment management and construction quality control. Tuc was blunt on the opening condition: the airport can only open after meeting all required conditions and ensuring absolute safety.

Access roads: a second race against the calendar

The Ministry of Construction said Long Thanh's operational capacity depends as much on transport connections as on airport infrastructure, and these factors will affect airlines' flight schedules and route planning. Access routes must handle peak-hour passenger traffic with high-quality public transport, parking and transfer arrangements between Tan Son Nhat and Long Thanh.

Travel from Ho Chi Minh City to Long Thanh currently relies entirely on roads. Several expressway sections and the An Phu interchange remain under construction and are expected to be largely completed only in early Q2-2027. Transport capacity and traffic arrangements cannot yet be fully assessed. Passengers have already raised concerns about travel times, congestion and the risk of missing flights, particularly when transferring between the two airports.

The ministry said convenient travel cannot be guaranteed from the outset if access routes are not fully connected when Long Thanh begins operations, and urged local authorities and Vietnam Expressway Corporation (VEC) to accelerate construction and prepare contingency plans for traffic disruptions and demand exceeding road capacity.

Ho Chi Minh City and Dong Nai authorities said they have established task forces and drawn up traffic plans for routes connecting to the airport.

The December 10 ministry report now sets the clock. Until it lands, carriers, forwarders and shippers planning around Long Thanh should assume phase 1 slips to 2027-28 and that road access — not runway capacity — may be the binding constraint in the airport's first months.

Source: news.tuoitre.vn

More from Tom Whitfield

Tom Whitfield

Show full bio

Market editor covering companies, deals and strategy in Ocean and air freight, container shipping at Waybill Wire.

1,019 articles

Related

  1. Long Thanh airport opens Dec 24 with 30 flights a day, $13bn bet

  2. 34 foreign airlines seek delay of Vietnam's Long Thanh airport move

  3. Vingroup Offers to Fund Temporary Hanoi Rail Station as $6.3bn Highway Build Looms

  4. Gia Binh Bets 1.6 Million Tons on Vietnam's Electronics Corridor

  5. Vietnam studies Gia Binh move with 1.6m-ton cargo target

« PrevNext »