34 foreign airlines seek delay of Vietnam's Long Thanh airport move

Thirty-four foreign airlines want a phased, delayed shift to Long Thanh airport, whose December 24, 2026 debut leaves cargo operators only about three months of trial runway.

By
James Calloway
Filed
Length
698 words
Read
3 min
34 foreign airlines seek to delay move to Vietnam's largest airport Long Thanh
34 foreign airlines seek to delay move to Vietnam's largest airport Long Thanhviarami / pixabay

Key points05

  • 34 foreign airlines have asked for a delayed, phased transfer to Long Thanh International Airport
  • Long Thanh targets a December 24, 2026 commercial launch with about three months of integrated trial operations
  • Technical preparation and assessment for cargo operations could take around 12 months, including a required US TSA on-site inspection
  • Phase 1 costs about VND109 trillion ($4.22 billion) with annual capacity of 25 million passengers and 1.2 million tonnes of cargo
  • Full build-out spans 5,000 hectares in Dong Nai City, more than $16 billion, 100 million passengers and 5 million tonnes of cargo a year

Thirty-four foreign airlines have asked Vietnam to delay the shift of international flying from Tan Son Nhat International Airport to Long Thanh International Airport, even as the project keeps December 24, 2026, as its planned commercial launch.

The request follows a survey by the Civil Aviation Authority of Vietnam, which found international carriers welcomed the new airport's infrastructure and service capacity but called for a transition roadmap they can absorb.

What are the airlines asking for?

"The airlines said relocating operations involves more than simply changing departure and arrival airports," the survey found. Adjusting flight networks, aircraft and crew arrangements, staffing, ground services and ticketing systems could take six to 12 months.

Foreign aviation authorities may also need to inspect the airport and approve safety conditions before carriers can operate there. Airlines also asked for improvements to medical services, four-star or higher transit hotels and convenient transport links with Ho Chi Minh City.

What does this mean for cargo operators?

To launch direct cargo services from Long Thanh to the United States, the U.S. Transportation Security Administration must conduct an on-site inspection and assessment of the airport.

International logistics companies such as UPS, FedEx, DHL and Cargolux also require coordinated facilities for express cargo terminals, customs clearance, truck handling and road connections. Technical preparations and assessments for cargo operations could take around 12 months.

Put those numbers against the launch date. The Airports Corporation of Vietnam has budgeted roughly three months of integrated trial operations, from late September until the late-December 2026 commercial start, under an operational readiness program of 55 scenarios spread across three phases from September to December 2026. A 12-month cargo assessment window does not fit inside a three-month runway.

How many flights are planned at opening?

Under the Airports Corporation of Vietnam's plan, Vietnam Airlines is expected to operate 72 flights per week at the initial stage, while Vietjet could operate up to 294 weekly flights. Both figures cover domestic services only.

How long do comparable airports test themselves?

  • Beijing Daxing International Airport, China: flight trials began in May 2019 ahead of a September 25, 2019 opening. Its sixth trial covered 100 simulated flights, more than 13,000 passengers and 9,000 pieces of luggage.
  • Istanbul Airport, Turkey: preparations started in May 2018, involving more than 100 scenarios and 63 days of testing. The airport handled roughly eight to 10 flights per day for about five months before completing the full transfer of operations in April 2019.
  • Hong Kong International Airport: drills started in January 1998. The final exercise involved around 12,000 people, 35 airlines and four aircraft ahead of the July 1998 opening.
  • Incheon International Airport Terminal 1, South Korea: about nine months between construction completion and commercial operation. Singapore Changi Airport Terminal 4: approximately 12 months.

There is no fixed trial period, aviation experts said, but multiple rounds of testing, fault detection, corrective work and retesting are essential to operational readiness.

What is Long Thanh built to handle?\n

Spanning 5,000 hectares in Dong Nai City, Long Thanh International Airport is set to become Vietnam's largest airport, with total estimated investment of more than US$16 billion. Developed in three phases, it is designed for up to 100 million passengers and five million tonnes of cargo annually at full completion.

Its first phase, costing approximately VND109 trillion ($4.22 billion), carries annual capacity of 25 million passengers and 1.2 million tonnes of cargo. The airport is expected to ease pressure on Ho Chi Minh City's Tan Son Nhat and become a major international aviation hub, while pulling infrastructure, industrial and urban development into the surrounding region.

Aviation experts called Long Thanh a nationally significant aviation infrastructure project where early operation matters, but said the schedule must be balanced with operational quality and efficiency. "A phased approach, aligned with the readiness of airport infrastructure, airlines and supporting services, would help minimize disruption for passengers and businesses," they said.

Whether December 24 holds now turns on how much of that 55-scenario readiness program, and the 12-month cargo preparation window, survives the airlines' push for a slower, staged transfer.

Source: news.tuoitre.vn

Share this article:

More from James Calloway

James Calloway

Show full bio

Correspondent covering companies, deals and strategy in Ocean and air freight, container shipping at Waybill Wire.

954 articles

Related05

  1. Canada Approves Direct Vietnam Flights, Vancouver-Ho Chi Minh City Possible by 2027

  2. Vingroup Offers to Fund Temporary Hanoi Rail Station as $6.3bn Highway Build Looms

  3. Top Liner to Back Vietnam's Regional Transshipment Hub Bid

  4. Hacis targets Vietnam cargo with new road feeder route to HKIA

  5. Vietnam studies Gia Binh move with 1.6m-ton cargo target

« Prev