Appeals Court Voids License Basis for $2.1 Billion Texas GulfLink Oil Port
A US appeals court voided the record of decision behind Sentinel Midstream's $2.1 billion Texas GulfLink crude export terminal, and Sentinel's own filings admit offshore work can't proceed on the current license.
- By
- Amara Osei
- Filed
- Length
- 601 words
- Read
- 3 min

Key points05
- The 5th US Circuit voided MARAD's record of decision for the $2.1 billion Texas GulfLink project; the mandate took effect October 30.
- The court found the approval violated the Deepwater Port Act because GulfLink's application area overlaps Enterprise's SPOT project.
- Sentinel aims to load supertankers with about 2 million barrels per day from a site 30 miles off Freeport, targeting Q4 2028 operations.
- Two other pending deepwater port applications will likely require redesignation under the ruling.
- Sentinel's original approvals took nearly seven years; MARAD has recently issued a license in 410 days.
A US appeals court ruling has stripped the legal foundation from Sentinel Midstream's $2.1 billion Texas GulfLink deepwater crude export terminal, and the company's own court filings concede offshore construction cannot proceed on the current license.
The 5th US Circuit Court of Appeals voided MARAD's record of decision for the project in August, and the mandate took effect October 30. The court found MARAD violated the Deepwater Port Act, which allows only one approved deepwater port per application area. Texas GulfLink's properly designated area would overlap with Enterprise Products Partners' Sea Port Oil Terminal (SPOT) project.
Sentinel received its license in January 2026, made a final investment decision in May, and started construction. Now that sequence is in doubt. The terminal, planned roughly 30 miles off Freeport, Texas, aims to fully load a supertanker with about 2 million barrels of crude per day.
What does the ruling change for shippers and operators?
For now, nothing on paper. Sentinel says its license has not been suspended or terminated. "It remains business as usual for Texas GulfLink, with site development and improvement activities currently underway at our Jones Creek onshore terminal facility as we prepare to commence tank construction," said Bruce Heine, a senior vice president at Sentinel. Heine said long-lead equipment and pipe have been purchased and key construction contracts executed, and the project remains on track for fourth-quarter 2028 operations.
The court record tells a different story. In an October motion to stay the mandate, Sentinel itself argued the license expressly incorporates the ROD as a compliance standard, and that voiding it "exposed the license to suspension or revocation by MARAD, and prevents construction of offshore components."
"At a minimum, the cloud on Texas GulfLink's regulatory posture will harm Texas GulfLink in the marketplace," the company wrote, adding it "will not commence construction of the deepwater port under the current posture, even if the mandate is stayed."
Public optimism, private caveats. Standard practice for a project this exposed.
Petitioners demand license revocation
Environmental group Better Brazoria Clean Air and Water, which petitioned the court, says construction cannot legally continue without a federal deepwater port license. "The Court's decision is clear: it vacated the record of decision that was the foundation of GulfLink's license. Now, MARAD has to revoke or suspend that license," Michael Brown, counsel for the petitioners, said Wednesday.
MARAD said it was disappointed and continues to pursue "all avenues" toward the president's energy-dominance agenda. A source familiar with the matter told Reuters that Sentinel "cannot continue with the current license" and is working with MARAD on options.
The court also held that a Deepwater Port Act application area must cover the entire proposed port site, pipelines included. That interpretation reaches beyond GulfLink: Sentinel says two other pending deepwater port applications with similar areas will likely require redesignation, with "consequential impacts" to those projects.
A seven-year problem, or a 410-day one?
If Sentinel must resubmit, it needs a fresh ROD and license. Its original approvals took nearly seven years. The arithmetic is less brutal under the current administration: MARAD recently issued a deepwater port license in 410 days — roughly 3.7 years faster than the historical average. The White House has also lately approved licenses for Energy Transfer's Blue Marlin Offshore Port off Louisiana and ST LNG's Texas liquefied natural gas export project.
Sentinel plans to petition the Supreme Court. The project's fate now turns on whether that petition lands, or whether GulfLink restarts a licensing clock that — even accelerated — measures in years.
Source: gCaptain
More from Amara Osei
Show full bio
Staff writer covering regulation, policy and their impact on Ocean and air freight, container shipping at Waybill Wire.
992 articles
Related05
MARAD Clears $8.2 Billion Offshore Texas LNG Port in 410 Days
US Gulf VLCC buildout: Texas GulfLink the lone project racing toward Q4 2028 start-up
MARAD Clears $1 Billion Blue Marlin Offshore Crude Port Off Louisiana
MARAD Cuts Deepwater Port Reviews by 70% Without Cutting Environmental Corners
Port Houston launches Project 12 study as Ship Channel growth continues