Vietnam Deploys 33-Tonne Rail Welder to Hit APEC 2027 Deadline
A 33-tonne flash-butt welding machine is laying 250-300 meters of rail daily on Phu Quoc, as 1,300 workers push the $344M railway toward its November 2027 APEC deadline.
- Desk
- Trucking & Rail
- By
- James Calloway
- Filed
- Length
- 551 words
- Read
- 3 min

Key points05
- The 33-tonne machine welds 250-300 meters of single rail per day, 3-4x faster than aluminothermic welding.
- The Phu Quoc urban railway costs about VND9 trillion ($344 million) and spans nearly 18 km with six stations.
- More than 11 km of track installed; all bored piles for bridge and tunnel sections are complete.
- Around 1,300 engineers and workers are deployed across seven construction fronts.
- Phu Quoc hosts the APEC Economic Leaders' Meeting in November 2027.
A 33-tonne mobile automatic rail-welding machine is churning out more than 20 welded joints a day on Phu Quoc Island, triple the pace of the conventional method, as Vietnam races to finish a VND9 trillion ($344 million) urban railway before APEC 2027.
The machine, deployed for the first time on the Phu Quoc urban railway project, completes a single rail joint in three to four minutes under favorable site conditions. It can weld 250-300 meters of single rail per day — productivity three to four times that of aluminothermic welding, the traditional technique used on many regional rail builds.
Nguyen Huy Thanh, a representative of the rail-welding contractor, said the deployment marked progress in technology adoption and the ability of Vietnamese workers to operate advanced equipment.
"The machine uses electric flash-butt welding technology," Thanh said. "The two ends of the rail sections are heated and pressed together using a specialized system, with technical parameters adjusted to suit each type of rail."
After each weld, engineers run a grinding machine over the joint to meet technical and aesthetic requirements. Engineers monitor every welding operation to ensure the joints let trains run smoothly and safely. Crews are working around the clock at the site in Phu Quoc Special Zone, An Giang Province, installing and aligning rails, tightening bolts and welding sections across multiple fronts.
How far along is the project?
Sun Group, one of Vietnam's leading real estate developers and the project's backer, said the contractor has mobilized around 1,300 engineers and workers across seven construction fronts.
The numbers so far:
- More than 11 kilometers of track installed to date
- All bored piles for the bridge and tunnel sections completed
- Reinforced concrete structures finished on the tunnel sections connecting DT.975 Road to Phu Quoc International Airport
- Rail installation in those tunnel sections scheduled to begin next
The nearly-18-kilometer line will have six stations featuring Vietnamese cultural elements. It is being built to serve APEC 2027 and improve transport infrastructure on the island.
Why the 2027 deadline matters
Phu Quoc hosts the APEC Economic Leaders' Meeting in November 2027, following previous Vietnamese editions in Da Nang in 2017 and Hanoi in 2006. The high-profile event is expected to accelerate infrastructure development, attract investment and give fresh momentum to the island's tourism and real estate sectors.
That puts a hard political date on the construction schedule. With roughly 7 kilometers of track still to lay and tunnel-section rail work only now starting, the welding pace — not design or permitting — becomes the binding constraint. The switch to flash-butt welding, which produces joints of consistent quality at machine speed rather than manual pace, is the contractor's answer.
The stakes run beyond one island. Vietnam is positioning itself as a manufacturing and logistics alternative in Southeast Asia, and island infrastructure that ties an international airport to a conference-grade urban corridor is the kind of fixed asset that outlasts the summit itself. If the line opens on schedule in 2027, Phu Quoc gains a permanent transit spine; if it slips, the island leans on road transport through peak APEC traffic.
For now, the 33-tonne machine keeps grinding joints at three-to-four-minute intervals, and the calendar keeps moving toward November 2027.
Source: news.tuoitre.vn