Seaway 7 lines up three-vessel fleet for 1.4GW Berwick Bank B
Seaway 7 will deploy the Alfa Lift, Strashnov and Phoenix on SSE's 1.4GW Berwick Bank B, installing some 90 foundations at 52m depths off Scotland from 2029.
- Desk
- Ocean Freight
- By
- James Calloway
- Filed
- Length
- 492 words
- Read
- 2 min
Key points05
- Seaway 7 will deploy three vessels on the 1.4GW Berwick Bank B project, with offshore work expected in 2029-2030
- The scope covers roughly 90 fixed-bottom turbine foundations in average water depths of about 52m, 38km off the Scottish Borders
- SSE named Seaway 7 preferred supplier in October; final investment decision is expected in late 2027
- Berwick Bank B forms part of the wider ~4.1GW Berwick Bank complex and would be the world's deepest fixed-bottom wind farm
- Preparatory construction could begin in 2028, with installation running into 2031
Seaway 7 is preparing to deploy a three-vessel installation fleet — the Seaway Alfa Lift, Seaway Strashnov and Seaway Phoenix — on SSE Renewables' proposed 1.4GW Berwick Bank B offshore wind development off Scotland, with offshore work pencilled in for 2029 and 2030.
The trio forms part of the Subsea 7 subsidiary's engineering, procurement, construction and installation package covering turbine foundations and inter-array cables. SSE named Seaway 7 preferred supplier in October, tasking it with the design, supply and installation of approximately 90 fixed-bottom turbine foundations.
The scale of the marine challenge is the headline number: Berwick Bank B sits around 38 km off the Scottish Borders in the outer Firth of Forth, in average water depths of approximately 52 m. SSE expects the project to become the world's deepest fixed-bottom offshore wind farm once completed.
What sits behind the contract?
Berwick Bank B is one element of the wider Berwick Bank offshore wind complex, which carries a proposed capacity of approximately 4.1GW. The B-phase deal, however, remains subject to final contract award and SSE's final investment decision, expected in late 2027.
The timeline is tight but defined. Subject to approval, preparatory offshore construction could begin in 2028, with foundation and cable installation continuing into 2031. That gives Seaway 7 a multi-year installation window — and a vessel commitment that will occupy heavy-lift and cable-lay capacity in the North Sea through the turn of the decade.
For the offshore construction market, the assignment matters beyond a single project. Three specialist vessels tied up on foundations and inter-array cabling between 2029 and 2031 tightens availability for competing North Sea rounds scheduled in the same period. Charterers and developers planning adjacent Scottish and UK waters projects will factor that into scheduling and pricing.
A familiar pairing?
Seaway 7 and SSE are not strangers. The contractor previously worked with the utility on the Beatrice and Seagreen offshore wind farms — both Scottish projects, both delivered into challenging North Sea conditions. That track record underpins the preferred-supplier status awarded in October.
The vessel line-up itself spans the key installation disciplines. The Seaway Alfa Lift brings specialist foundation transport and installation capability, while the Seaway Strashnov and Seaway Phoenix round out the heavy-lift and support requirements across the foundation and inter-array cable scope.
What happens next?
Nothing is locked until SSE's final investment decision lands, expected in late 2027. Until then, Seaway 7's fleet assignment remains a planned deployment rather than a contracted one — but the October preferred-supplier selection signals both parties' intent to proceed.
If the investment case holds, preparatory offshore construction starts in 2028, the three-vessel fleet mobilises for the 2029–2030 installation seasons, and foundation and cable work runs into 2031. Watch the late-2027 decision date: it converts a proposed 1.4GW development and its roughly 90 foundations from planning documents into firm offshore logistics.
Source: Splash247
More from James Calloway
Show full bio
Correspondent covering companies, deals and strategy in Ocean and air freight, container shipping at Waybill Wire.
976 articles
Related05
Fugro lands East Anglia Two seabed survey work worth covering 64 monopiles
HEA Energy to buy Subsea7’s six-vessel heavy transport unit
Port of Blyth Unveils $265M Clean Energy Expansion Program
Cadeler’s Wind Apex takes 87-turbine Dogger Bank C assignment
Meyer Werft creates Neptun Offshore to manage $2.8bn converter push