Mountpark starts 641,611 sq ft Ferrybridge logistics build

Mountpark has started Unit 3 at Ferrybridge, a 641,611 sq ft cross-docked facility with 18-metre eaves, 13MVA of power and Q4 2027 completion at the former power station site.

By
Amara Osei
Filed
Length
675 words
Read
3 min
Mountpark Ferrybridge commences construction
Mountpark Ferrybridge commences constructiontianya1223 / pixabay

Key points04

  • Construction has started on Mountpark Ferrybridge Unit 3, a 641,611 sq ft cross-docked logistics facility.
  • Vertical construction is scheduled for November 2026, with practical completion in Q4 2027.
  • The building has 18-metre clear eaves, two 50-metre service yards and access to up to 13MVA of power.
  • Unit 3 targets BREEAM Outstanding and an EPC A+ rating, with potential rail connectivity.

Mountpark has begun construction on a 641,611-square-foot cross-docked logistics facility at Mountpark Ferrybridge in West Yorkshire, with practical completion scheduled for the fourth quarter of 2027.

The speculative development, called Unit 3, forms the next stage in the transformation of the former Ferrybridge Power Station site. Its floor area covers roughly 14.7 acres, but floor space earns the headline; height, yards and power do the commercial persuading.

What is Mountpark building at Ferrybridge?

Planning consent was secured earlier this year, after which Mountpark moved immediately into site-enabling works. Those works prepare the site for vertical construction of Unit 3 in November 2026, before the building reaches practical completion in Q4 2027.

That is a long delivery window. Shippers cannot treat the practical-completion quarter as immediate warehouse capacity, although the published programme gives occupiers time to plan their requirements.

Which occupiers is the building designed for?

Mountpark describes Unit 3 as substantial XL logistics space for the northern market and calls its specification market-leading. It has 18-metre, or roughly 59-foot, clear internal eaves, two 50-metre service yards and Grade A headquarters-style office accommodation.

The eaves should accommodate tall storage systems, while the two service yards provide external space for vehicle movements. The office component adds a headquarters setting to the industrial floorplate rather than leaving the building as a warehouse and nothing more.

For shippers and contract logistics operators, the combination means a large, high-clearance facility with room for substantial vehicle handling and office functions on one site. It does not identify a tenant, cargo type or transport mode, so it would be premature to count Unit 3 as dedicated freight demand.

How significant is the 13MVA power connection?

Unit 3 will have access to up to 13MVA of power, which Mountpark says supports occupiers with significant operational and energy requirements. For businesses with energy-intensive operations, that availability could influence site selection, although the announcement names neither intended users nor individual loads.

The development also has potential for rail connectivity, offered as support for occupiers’ decarbonisation strategies. Mountpark is targeting BREEAM “Outstanding” certification and an EPC “A+” rating, making those credentials stated design targets rather than confirmed operating results.

What does this change for shippers and forwarders?

If completed, Unit 3 will add a substantial large-format option to the northern UK logistics market, with 641,611 square feet the headline number. For shippers, third-party logistics providers and forwarders, the useful test is whether its height, yards, power and possible rail interface fit a specific operation.

No tenant or freight operator has been named, and the announcement includes no rail operator, service timetable or committed freight volume. The project should therefore be treated as future capacity, not confirmed throughput, until Mountpark provides more detail.

Brett Huxley, development director for Mountpark UK & Ireland, said:

“Starting construction on Unit 3 marks another major milestone for Mountpark Ferrybridge and demonstrates our commitment to delivering a high-quality development pipeline at scale.

“With a committed delivery programme in place, we’re providing occupiers with the certainty they need to plan their future operations.

“The combination of the building’s specification, strategic connectivity and up to 13MVA of power makes Unit 3 particularly well suited to businesses with substantial operational requirements.”

For occupiers, the practical effect is advance planning. A business that needs large eaves, two 50-metre yards and substantial electricity can assess Unit 3 as a long-term option now, rather than waiting until the building nears completion.

When will the capacity arrive?

Site-enabling works are progressing, vertical construction is scheduled for November 2026, and practical completion is due in Q4 2027. That sequence leaves 2026 and most of 2027 without the finished capacity.

The next delivery test is whether vertical construction starts on schedule in November 2026. If Mountpark meets its programme, Unit 3 will bring 641,611 square feet of northern logistics space into operation in late 2027, with power and rail connectivity shaping how much of it occupiers can use.

Source: Logistics Manager

Share this article:

More from Amara Osei

Amara Osei

Show full bio

Staff writer covering regulation, policy and their impact on Ocean and air freight, container shipping at Waybill Wire.

950 articles

Related05

  1. Chancerygate submits 153,000ft² logistics scheme at Coleshill

  2. Peel Ports to Add One Million Sq Ft of Warehousing Across UK Network

  3. £1.5bn Oxfordshire Rail Freight Interchange enters six-month planning test

  4. Liverpool port rail share stuck at 2% as Peel Ports expands terminal

  5. Marshall CDP starts 193,500ft² speculative build at Deeside Airfields

« PrevNext »