Jangani bridge reaches 41% under Dar es Salaam’s $260m flood plan
TANROADS says the 390-metre Jangwani bridge is 41% complete. The US$260 million basin program seeks uninterrupted BRT and road access while expanding flood controls through 2028.
- Desk
- Trucking & Rail
- By
- Elena Vasquez
- Filed
- Length
- 1,036 words
- Read
- 5 min

Key points05
- In August, TANROADS said the 390-metre Jangwani bridge was 41% complete and would stand about eight metres above the existing road.
- About 496 piles are required; officials had completed 404 at depths of 35 to 42 metres.
- The project package is about US$260 million, including US$200 million in IDA concessional financing, and runs through 2028.
- The basin holds about 1.6 million people; a 2018 flood caused US$100 million in damage, roughly 2% of city GDP.
- Around 3,500 floodplain households were targeted for relocation with US$30 million allocated for compensation.
By Elena Vasquez
TANROADS reported in August that construction of Dar es Salaam’s 390-metre Jangwani bridge had reached 41%, with the crossing set about eight metres above the existing road. The elevated span forms the centerpiece of a wider program designed to protect one of the city’s busiest routes from recurrent Msimbazi flooding.
Each morning on her bus to Kariakoo, 37-year-old shopkeeper Clementina Nyangwine watches foundation piles rise above the muddy Msimbazi valley. During earlier floods, she spent hours waiting for water to recede near Jangwani and sometimes walked through mud after leaving a stalled bus. She once reached her shop with clothes soaked in filthy water.
Passengers once waited at the edge of Morogoro Road as murky floodwater swept across the carriageway, turning a one-hour trip into four. Nyangwine sometimes reached her Kariakoo shop late and found that customers had already left, while another downpour could turn her journey home into the same ordeal.
What does the crossing add to Dar es Salaam’s road network?
The bridge forms part of the Msimbazi Basin Development Project, which seeks to reduce chronic flooding as climate risks intensify. Its 1.2-kilometre construction corridor includes approach roads, while the bridge itself will stand roughly 41 metres wide. The structure must carry vehicles, pedestrians, cyclists and the city’s Bus Rapid Transit system.
Work rests on roughly 496 deep foundation piles, of which officials had completed 404. Depending on soil conditions, the piles extend between 35 and 42 metres underground, supporting the crossing in the muddy valley floor.
Project manager Leonard Ngayungi said the existing road sat within an active floodplain, so rising water turned the carriageway into part of the flood area. The new design would restore the river’s uninterrupted flow beneath a transport route that buses, pedestrians and other vehicles could continue using. “We have to build for the rainfall we may face in the future, not simply the rainfall patterns people remember from 20 or 30 years ago,” he said.
How does flooding disrupt transport and commerce?
The Msimbazi is a relatively small river with an outsized effect on Dar es Salaam. Its basin contains about 1.6 million people in densely populated neighborhoods. Near Jangwani, two major traffic arteries cross the lower floodplain, including the corridor used by the city’s first BRT system.
The reported effects are concrete: roads close, buses stop, workers arrive late, traders lose customers, and goods cannot move easily between the city centre and western suburbs. For shippers relying on urban road distribution, road carriers and freight forwarders, the immediate commercial benefit is journey continuity rather than a stated increase in freight capacity.
The elevated crossing is intended to remove a recurring interruption point from that road link by keeping buses and other vehicles above the flood level. Majega believes that, if the bridge performs as designed, rain will no longer require the entire route to stop at Jangwani.
Issa Majega, 56, a BRT driver on the Kariakoo-Kimara route, said heavy rain turns a routine journey into hours of uncertainty. Passengers become stranded, traffic builds on alternative roads, and drivers must wait rather than gamble with a full bus in moving water.
Can the basin absorb heavier rainfall and urban growth?
Dar es Salaam’s flooding cannot be attributed to rainfall alone. Rapid urban sprawl has pushed settlements into wetlands and floodplains, while buildings and roads have reduced the land available to absorb rainwater. Rubbish obstructs drainage channels, and sediment has accumulated in parts of the Msimbazi.
About 70 percent of Dar es Salaam’s residents live in informal settlements, many with inadequate drainage. A major flood in the Msimbazi basin in 2018 caused an estimated US$100 million in damage, equivalent to roughly 2 percent of the city’s gross domestic product, according to World Bank figures.
Deusdedit Rwehumbiza, an urban planning professor at Mkwawa University in Iringa, says the visible bridge cannot solve the underlying watershed problem by itself. He argues that the project’s strength lies in treating land use, environmental management and transport as one system.
River improvements, floodplain restoration, watershed management and better solid-waste controls accompany the crossing. Parts of the lower basin are intended to become flood-detention areas that temporarily hold excess water instead of forcing it through occupied neighborhoods.
Who pays for the work, and who must move?
About 3,500 households in the floodplain were targeted for resettlement, with US$30 million allocated for compensation. Teresia Katimba, a mother of four, moved to Madale in 2024 after years of floods repeatedly filled her Jangwani home with sewage and rubbish.
Rwehumbiza cautions that safer homes will not deliver climate resilience if displaced families cannot afford transport to work and livelihoods. Relocation can remove exposure to the river while still creating a transport barrier to employment.
The World Bank’s International Development Association is providing US$200 million in concessional financing. Spain and the Netherlands are contributing additional financing, bringing the package described by Tanzanian authorities to about US$260 million.
The program will run through 2028 across the lower Msimbazi basin, with work extending upstream toward the Pugu Hills. TANROADS leads the Jangwani bridge works, while other government institutions participate in the wider valley redevelopment. Authorities also envisage markets, commercial development and improved public transport in the redeveloped valley.
Will the bridge remove the bottleneck?
The structure will not prevent heavy rain, and one crossing cannot make Dar es Salaam climate-proof. Its performance will depend partly on upstream waste control, sediment management and development, according to Rwehumbiza, who said a bridge may last decades while the connected river system requires continuous attention.
For commuters, the test will come on a rainy morning when the Msimbazi rises but buses and road traffic can cross without stopping. “The river will still flood when the rain is heavy,” Nyangwine said. “But if people can cross safely above it, then the rain does not have to stop our lives.”
Through 2028, the program’s remaining works and basin controls will test whether the 390-metre crossing can deliver reliable BRT and road access without shifting flood risk to relocated households or leaving upstream controls unresolved.
Source: africa.com
More from Elena Vasquez
Show full bio
News editor covering people, launches and day-to-day practice in Ocean and air freight, container shipping at Waybill Wire.
945 articles
Related05
Central Vietnam floods cut highways and suspend Ly Son ferry links
Central Vietnam floods cut roads and schools, but reservoirs stay dry
Tanzania sets 1,500-container daily rail target to ease Dar backlog
Ha Long Proposes $996mn Dual-Level Sea Bridge with Air Taxi Pad
Tanzania bets rail can fix Dar es Salaam port gridlock