Heathrow third runway slips to 2039 as airport logs 1.5m tonnes in 2025
Heathrow has rowed back its third runway opening from 2035 to as late as 2039, calling the earlier date 'ambitious.' The airport cleared 1.5m tonnes in 2025 and launches an eight-week consultation on 27 October.
- Desk
- Air Cargo
- By
- Amara Osei
- Filed
- Length
- 426 words
- Read
- 2 min

Key points05
- Heathrow puts third runway opening closer to 2039 than 2035, citing 2029 planning target.
- Airport handled 1.5m tonnes of cargo in 2025, up 0.8% year on year.
- UK cargo rose 29.7% and North America volumes gained 4.6% in 2025.
- 2026 Public Consultation runs 27 October to 22 December, eight weeks.
- Runway scheme includes a 3.5 km strip and M25 tunnel, selected by UK government in November 2025.
Heathrow Airport has signalled that its third runway will open closer to 2039 than 2035, pushing the UK's most-watched aviation capacity project toward the back end of a decade-long build window.
The London hub framed the earlier 2035 date as unrealistic in a statement to Reuters. "Our focus has always been to secure planning permission by 2029," a Heathrow spokesperson said. "Once achieved the runway will be open within a decade." That wording reflects the UK government's timetable, issued in January 2026, which set planning consent as a 2029 milestone and capped opening at 2039.
What changed in the timeline?
Heathrow's first-quarter 2025 results, published 30 April 2025, had aimed for a 2035 operational date. Seven months later, the operator publicly hedged. The shift matters for shippers because air cargo capacity at LHR is already constrained on key long-haul lanes.
How does the cargo side weigh in?
Heathrow moved 1.5 million tonnes of freight in 2025, up 0.8% year on year. The growth was driven by a 29.7% surge in UK-origin cargo and a 4.6% rise in North America tonnage. That performance gives the airport a hard-data case when it argues for a third runway, but it also exposes how little slack exists today.
What is the consultation path?
Heathrow will open its 2026 Public Consultation on 27 October, running for eight weeks to 22 December. Local residents and logistics stakeholders will review expansion plans before a planning application is submitted. Funding for that application was approved in January 2026, a move trade body Logistics UK welcomed at the time.
Why is the runway design complicated?
The Heathrow Northwest Runway scheme, sponsored by Heathrow Airport Limited (HAL), covers a 3.5 km strip and a tunnel for the M25 motorway. The government selected the design in November 2025, calling it "the most credible and deliverable option" for the Airports National Policy Statement review.
What does it mean for freight operators?
- Two more years of tight belly-hold capacity on transatlantic and Asian lanes, with no new runway slot to absorb demand.
- Continued pressure on the airport's 'Horseshoe' cargo area, where HAL is mid-redevelopment alongside a stakeholder-led upgrade.
- Wider use of the CCS-UK AIS trucking portal for booking and monitoring landside slots — a system HAL says is already easing drayage friction.
Forwarders using LHR as a pharma or e-commerce gateway should expect slot constraints to persist through the late 2030s, even as Heathrow pushes toward its 2029 planning milestone.
Original: reuters.com
More from Amara Osei
Show full bio
Staff writer covering marketplaces and e-commerce at Waybill Wire.
257 articles
Related05
Heathrow Pushes Third Runway Opening to 2039, Extending Cargo Capacity Wait
Heathrow Third Runway Backers Demand 'Spades in the Ground'
GMB Union Demands 'Spades in the Ground' on Heathrow Third Runway
Air Canada Cargo clocks one year on terminal modernisation drive
Cathay Cargo adds five weekly freighters to four US, Mexico gateways