Allseas taps Aker Solutions for Statfjord A topside removal job
Aker Solutions has secured a NOK500m-NOK1.5bn letter of intent to dismantle Equinor's 50,000-tonne Statfjord A topside at Stord, with Pioneering Spirit handling the single lift.
- Desk
- Ocean Freight
- By
- Amara Osei
- Filed
- Length
- 520 words
- Read
- 3 min

Key points05
- Letter of intent valued at NOK500m-NOK1.5bn ($52m-$155m) for Statfjord A topside dismantling
- The ~50,000-tonne topside will be lifted in a single operation by Pioneering Spirit, rated at 60,000 tonnes
- Topside arrives at Stord between 2029 and 2031; dismantling takes about two years with ~100 peak personnel
- Aker Solutions expects to book the contract in Q4 2026, subject to final award
- Statfjord A began production in November 1979 and was originally built at Stord in the 1970s
Aker Solutions has landed a letter of intent from Allseas worth between NOK500m and NOK1.5bn ($52m to $155m) to dismantle and recycle Equinor's Statfjord A platform topside in the North Sea.
The contract covers preparatory work, reception, dismantling and recycling of the roughly 50,000-tonne structure at Aker Solutions' Stord facility in western Norway. To put that weight in perspective: it's nearly three times the 18,000-tonne Gyda topside Allseas delivered to the same yard for recycling in 2022.
Aker Solutions classifies the job as "sizeable" and expects to book it in the fourth quarter of 2026, subject to a final award. The Stord yard knows this particular steel well — Statfjord A was originally constructed there in the 1970s.
How do you move 50,000 tonnes of platform?
In one lift. Allseas will remove the topside using its heavy-lift vessel Pioneering Spirit, hoisting the structure off its concrete gravity-based foundation in a single operation. The vessel's upgraded lifting system is now rated at 60,000 tonnes, which gives it comfortable headroom over the payload.
Pioneering Spirit has form here. It handled the Gyda removal for the same client pairing, and that project established the template: single lift, tow to Stord, cut up onshore.
The topside should arrive at Stord between 2029 and 2031. Dismict dismantling and recycling will then take roughly two years, with around 100 personnel working on the project at peak activity.
What does this change for the North Sea decommissioning market?
Quite a lot, if you're a yard competing for late-life work. The deal confirms Stord as the default destination for Norwegian heavyweight recycling, and it extends Aker Solutions' order visibility well into the next decade — the revenue lands in the book from Q4 2026, but the physical work stretches toward the mid-2030s.
For Allseas, the contract locks in the onshore leg of a campaign it has been assembling piecemeal since 2019, when Equinor and Allseas first announced arrangements for removing and recycling the structure. Kvaerner — subsequently integrated into Aker Solutions — was selected for the onshore work at that time, so the letter of intent is less a surprise than a formalisation of a long-running plan.
More recently, Allseas appointed consultancy ABL as marine warranty surveyor for the removal campaign, adding a third major contractor to the roster.
A platform with nine lives
Statfjord A began production in November 1979 and has undergone several life extensions since. Nearly half a century later, the North Sea's original giant fields are moving into their removal phase, and each topside of this scale represents a multi-year engineering and logistics exercise rather than a simple demolition job.
The single-lift method pioneered by Pioneering Spirit has shortened the offshore portion of such projects considerably, but the onshore side — reception, dismantling, recycling — remains a two-year commitment requiring a hundred-strong workforce at peak.
Expect more awards of this shape. Norway's maturing field portfolio guarantees a pipeline of topsides, and the carriers that can pair heavy-lift vessels with guaranteed yard capacity will keep winning the work.
Source: Splash247
More from Amara Osei
Show full bio
Staff writer covering regulation, policy and their impact on Ocean and air freight, container shipping at Waybill Wire.
950 articles
Related05
Stockholm Norvik Inaugurates Aggregate Loading Facility for Baltic Bulk Trades
Saronic Signs $100 Million-Plus Deal for World's Largest Shiplift
2020 Bulkers taps offshore veteran Babinski as CEO after AHTS pivot
Seanergy bulk-buy hits $855m as four more ships join fleet push
HEA Energy to buy Subsea7’s six-vessel heavy transport unit