Albayrak's African port empire: $5bn promised, little delivered
Albayrak Group has pledged up to $5bn across African port concessions, but auditors in Somalia and renegotiations in The Gambia expose a widening gap between promises and delivery.
- By
- Elena Vasquez
- Filed
- Length
- 746 words
- Read
- 4 min

Key points05
- Albayrak operates eight ports in seven countries under its ALPORT brand, having entered ports in 2003 at Trabzon.
- Mogadishu's renegotiated 2020 concession uses a 45%-55% revenue split, but Somalia's Auditor General still cannot obtain timely audited accounts.
- A 28 September 2026 announcement cited up to USD 4 billion of Turkish investment in the New Mogadishu Port Project, awarded without a tender.
- Albayrak pledged USD 500m for Conakry, EUR 600m for Banjul/Sanyang, EUR 400m for Pointe-Noire and EUR 300m for Equatorial Guinea.
- The Gambian port authority told the National Assembly it is renegotiating key terms as the Sanyang deep-water project stalls.
Turkey's Albayrak Group has signed African port concessions carrying combined investment pledges approaching $5 billion since 2018, yet in Somalia, Guinea and The Gambia governments and auditors are struggling to verify even basic financial compliance. Mogadishu, Somalia's largest port and the federal government's single biggest revenue source, sits at the centre of the controversy.
Albayrak entered the ports market in 2003 with a 30-year operating right over Trabzon on Turkey's Black Sea coast, after starting life in construction in 1952. Under its ALPORT brand, it now controls eight ports in seven countries: Trabzon, Mogadishu (2013–14), Conakry's conventional terminal (2018), Pointe-Noire in Congo-Brazzaville (January 2024), Banjul in The Gambia (February 2025), Malabo and Bata in Equatorial Guinea (signed November 2024), and Alat in Azerbaijan.
The early expansion tracked Turkish diplomacy closely. Mogadishu followed Ankara's high-profile engagement in Somalia from 2011, while Conakry rode on ties between Presidents Erdoğan and Alpha Condé. Several awards were made by direct negotiation rather than open tender, pointing to political clout rather than competitive selection.
What went wrong in Mogadishu?
Somalia's federal government formally handed Mogadishu port to Albayrak in September 2014 on a 20-year term, with Albayrak as the only bidder. Since then, the company has unilaterally reduced the government's revenue share and underinvested relative to the original agreement, triggering legal disputes.
The IMF's 2019 Article IV consultation for Somalia listed further progress on renegotiating the Mogadishu port contract among the reforms tied to revenue mobilisation and the country's path to HIPC debt relief. A renegotiated 14-year concession followed in October 2020, built on a 45%–55% revenue-sharing model.
Transparency has not followed. Somalia's Office of the Auditor General has struggled to obtain timely audited financial reports to verify government revenue, and the country's Financial Governance Committee has flagged both the lack of transparency and high port costs imposed on users. In June, Auditor General Ahmed Guutaale met representatives of Mogadishu Al-Port Corporation to press for audited reports on time, stressing the port's role as the state's biggest revenue earner.
The pattern extends to the New Mogadishu Port Project. In February 2026 the Somali Ports Minister said feasibility studies were complete and the project had entered the tender phase, inviting investors to participate. Multiple port operators report no tender process took place. Instead, on 28 September 2026 Prime Minister Hamza Abdi Barre announced an agreement with Turkish investors covering the new port, a special economic zone and industrial developments, with figures of up to USD 4 billion in investment cited — a sum Port Strategy assesses as a "very long-term project" while operations continue in the existing port.
Where else have commitments fallen short?
Since Somalia, Albayrak has kept signing contracts promising billions in investment, far above what it can feasibly recoup:
- Conakry, Guinea (2018): a 25-year concession over the non-container terminal, awarded without tender, with a USD 500 million investment commitment. How much will actually be spent remains unclear. Reported problems include opaque concession procedures, a revenue split described locally as "the rip-off of the century", staffing and labour disputes, missed infrastructure commitments and severe port congestion.
- Banjul, The Gambia (2024): awarded through a formal tender supervised by Dutch consultancy MTBS, with EUR 600 million quoted to expand Banjul Port and build a new deep-water port at Sanyang within six years. The Sanyang project is not progressing, and the Gambian port authority has told the National Assembly it is renegotiating key terms.
- Pointe-Noire, Congo-Brazzaville (2024): a 25-year concession to modernise and operate conventional cargo terminals, with EUR 400 million promised.
- Equatorial Guinea (November 2024): EUR 300 million promised across Malabo and Bata, in a country of two million people.
Why does this matter for shippers and carriers?
For carriers and cargo owners on these trade lanes, the consequences are concrete: congestion at Conakry, high port costs at Mogadishu, and stalled capacity projects at Banjul that were meant to shift operations to deep-water facilities within six years. Each unfulfilled commitment leaves West and East African conventional and container capacity tighter than concession documents promised.
It is hard to envisage these investments being actively pursued at scale — many of the commitments clearly extend beyond business realities. With Banjul's renegotiation ongoing and Mogadishu's new-port deal struck outside any visible tender, further scrutiny of Albayrak's delivery record looks inevitable.
Source: portstrategy.com
More from Elena Vasquez
Show full bio
News editor covering people, launches and day-to-day practice in Ocean and air freight, container shipping at Waybill Wire.
929 articles
Related05
Hormuz Diversion Winners: Duqm Connectivity Up 213%, Khor Fakkan 188%
Medkon Lines adds Algiers call to Turkey–North Africa service
Maersk reshapes Europe–West Africa network from October 2026
Guinea seeks $1.9bn for 20-metre-draft deep-water port
MSC swaps Abu Qir for Damietta on EMUSA transatlantic loop